The presented chart of the history of the port allows you to see the process of development of the port, the important milestones in its construction and commissioning.
December 4, 2012.
Date of establishment of Sukhodol Seaport LLC
August 2013.
Signed contracts of lease of land for 49 years for the construction of the port with the possibility of subsequent redemption into ownership
2013
Start of engineering for the construction of non-public railway tracks with adjunction to Smolyaninovo station
May 12, 2014.
The project to build the Sukhodol seaport in the village of Romanovka, Shkotovo District, was successfully discussed with the local residents
November 2015.
Adoption of the Sukhodol seaport project in Glavgosekspertiza
February 2018.
Успешное прохождение Главгосэкспертизы проекта ж/д путей необщего пользования с примыканием к станции «Суходол»
March 15, 2018.
Signing of an agreement with Rosmorport on dredging to projected levels
May 17, 2018.
Sukhodol Seaport LLC became a resident of the Free Port of Vladivostok
IV quarter 2018.
Contracts with the General Contractors of the Project are signed. Start of port construction.
February 2019.
Signing of an agreement with the general contractor RZD-stroy JSC for the construction of non-public tracks with adjacency to Smolyaninovo station
December 31, 2019.
Signing of a syndicated loan agreement on project financing between the Project Participants, VTB PJSC and VEB.RF
September 2020.
Representatives of the Seaport "Sukhodol" participated in the Eastern Economic Forum
November 26, 2021.
Decree of the Government of the Russian Federation on inclusion of the Seaport of Sukhodol into the Seaport of Vladivostok was issued
December 2021.
Technological equipment was delivered to the construction site of the Sukhodol sea port in full
February 2, 2022.
Commissioning of the 220/10kV power substation at the Seaport of Sukhodol
February 25, 2022.
The project to build the Sukhodol seaport in the village of Romanovka, Shkotovo District, was successfully discussed with the local residents
August 2022.
Test transshipment of grain products for export from the Universal pier № 3 of the Seaport of Sukhodol was successfully completed.
II-III quarter of 2023.
The first coal transshipment in the Seaport of Sukhodol took place.
May 2023.
The first trainload of coal from Kuzbass arrived at the seaport of Sukhodol
December 2023.
Sukhodol seaport transshipped 2 million tons of coal in a year
December 2024.
Sukhodol sea port handled 6 million tons of coal in a year
January 2025.
Construction of a new terminal started at the seaport of Sukhodol