специализированный морской порт
на юге Приморского края с собственной железнодорожной инфраструктурой

Sukhodol seaport is an investment project created to facilitate access to port infrastructure for small and medium-sized coal mining companies.

Construction is carried out on the basis of the order of the Government of the Russian Federation dated March 19, 2013 № 384-r, in the water area of Telyakovsky Bay, Shkotovsky District, Primorsky Territory. The project is a participant of the Federal Project: "Development of Sea Ports".

Read more about the port ⟶
197 га

общая площадь порта

icons / icon_port_80 / moshnost 80 мВА

мощность питающей подстанции

icons / icon_port_80 / osadka 15,4 м

осадка судна в грузу

icons / icon_port_80 / conveyer 8 000 м

длина конвейерных линий

icons / icon_port_80 / jd 20 путей

на железнодорожной ст. «Суходол»

icons / icon_port_80 / vagoni 2,5 мин

скорость разгрузки вагонов на вагоноопрокидывателе тандемного типа

icons / icon_port_80 / kran 7 000 т/час

скорость погрузки угля на суда двумя СПМ

icons / icon_port_80 / sklad 915 тыс. т

ёмкость угольных складов

icons / icon_port_80 / ecology более 10

способов защиты окружающей среды от загрязнения

Request for cargo

Specialized seaport in the Shkotovo district of Primorye

Географическое положение

Выгодное географическое расположение порта в районе бухты Суходол по отношению к существующей (и создаваемой) транспортной инфраструктуре муниципального района и к населенным пунктам юга Приморского края.

Налоговые льготы

Морской Порт «Суходол» расположен в Шкотовском муниципальном районе Приморского края, который входит в состав территории Свободного Порта Владивосток, имеющей льготный налоговый режим.

Специальное техническое оснащение

Наличие необходимых территориальных резервов для размещения современных терминальных комплексов, способных принимать суда с осадкой до 15,4 м.

Круглогодичная навигация

Ледовый режим района не препятствует регулярной навигации по сложившимся маршрутам в течение всего года. В особо холодный период, для обколки прибрежного льда возможно задействование буксиров ледового класса.

Port development

Read more ⟶
Read more ⟶
Being Designed

Development zone of enterprises of the construction complex

Being Designed

Industrial Complex Development Zone

Being Designed

Shipbuilding zone

Being Designed

Fish cluster

In the Seaport of Sukhodol it is planned to build a refrigerating complex for receiving and transshipment of frozen fish products, as well as transshipment of live seafood (crab).

Being Designed

Bunkering base

The project of the Seaport "Sukhodol" provides for the construction of its own bunkering base, designed to supply ships with fuel and oil. The construction of the base has not started.

Being Designed

Sorting station No. 2

Being Designed

Construction base

Being Designed

Transport and repair area

As part of the prospective development of the Seaport "Sukhodol" plans to build its own repair area for vehicles and special equipment.

Being Designed

Main 220/27,5/10 kV step-down substation

For power supply of the Seaport "Sukhodol" we built our own 220/27,5/10 kV power substation. The facility was put into operation on 03.02.2022.

Being Designed

Logistics-industrial zone

The logistics area of the Seaport "Sukhodol" plans to place on its territory a logistics-industrial zone, which will accommodate warehouses for storage and sorting of cargo, the formation of small shipments and prefabricated containers.

Being Designed

Grain terminal

The seaport «Sukhodol» is developing a project of a grain terminal with fully automated system of management and control over loading of grain products. The design capacity of the terminal is expected up to 6 million tons/year.

More
Under Construction

Port Sukhodol railway station

The seaport Sukhodol has its own railway station Port Sukhodol. It consists of 20 tracks with a total length of 26 km. The station is 90% ready.

More
Being Designed

Mineral fertilizer terminal

The construction project of the Seaport Sukhodol provides for a Mineral Fertilizers Terminal. Estimated cargo turnover of the mineral fertilizers terminal is 2.0 million tons per year. The construction of the terminal has not started.

More
Being Designed

Container terminal

The seaport Sukhodol plans to build a modern complex specializing in the transshipment of container and general cargo.

More
Under Construction

Universal pier

Universal pier of the Seaport Sukhodol is designed for reception and handling of ships, transshipment of bulk cargoes. Cargo turnover of the berth is 2 million tons per year. The facility is being prepared for commissioning.

More
Under Construction

Coal terminal

Construction of a coal terminal for the receipt, storage and loading of coal from rail transport to sea vessels is nearing completion. The capacity of the coal terminal will be 12 million tons per year with a possible increase to 20 million tons per year. Commissioning is scheduled for 2023.

More
Being Designed

LPG terminal

It is planned to develop a specialized terminal for storage and transshipment of liquefied hydrocarbon gas (LHCG). It is planned to build steel vertical tanks for LPG storage. The construction of the terminal has not started.

More
Being Designed

Methanol terminal

The construction project of the Seaport Sukhodol provides for the Methanol Terminal. Design capacity of the marine cargo front of the Terminal is 2604 thous. tons per year and allows to handle the estimated turnover of 2,0 mln. tons per year. Construction of the terminal has not begun.

More
Being Designed

LNG terminal

In the Seaport of Sukhodol the territory for construction of a specialized terminal for storage and transshipment of liquefied natural gas (LNG) is laid out by the project. The planned turnover of the LNG Terminal will be 1.5 million tons per year. The construction of the terminal has not started.

More

Port area layout

Select the object you are interested in on the chart for information.

News & Events

Press Center ⟶